PHASE THREE FACTORY ROOFING

Project: Factory Re-roofing (Phase 3)

Client: Lindum BMS

Location: Lincoln

Timescale: Five weeks

Operations Manager: Nick Coughlan

Supervisor: Chris Hall

As part of a successful, ongoing wider project to replace all the roofing at a major engineering factory in Lincoln, Phase Three saw the removal and disposal of asbestos coated boards lining the underside of the roof structure in one large area of the site.

Rilmac Scaffolding provided the access and safety scaffolding, along with a protective false floor which allowed work in the factory below to continue unhindered.  Additionally, an 18m reach, 800kg capacity scissor lift was used to transport materials to the roof gully, and to remove all waste in secure containers.

This approach allowed for skylights and non-asbestos roof and gable end wall panels to be removed for use as access and egress airlocks, waste bag locks, and for the installation of Negative Pressure Units.  Thus, no hazardous waste was transported through the factory at all and was all removed externally instead, making the project safer still.

In total approximately 700m2 of asbestos coated fibre board were safely removed and disposed of by a highly trained team of six operatives over just 23 days.

Call us on 0800 612 9002 or
Request a Quote


Contact Numbers

Rilmac Asbestos - Lincoln
Crofton Drive, Allenby Road Industrial Estate, Lincoln, Lincolnshire LN3 4NJ

Tel: 0800 612 9002
Fax: 01522 510291

Rilmac Asbestos - London
5 Cecil Court, Pegrams Road, Harlow, CM18 7QR

Tel: 0800 612 9002

Rilmac Asbestos - Manchester
Unit D21 Fieldhouse Industrial Estate, Fieldhouse Road, Rochdale, OL12 0AA

Tel: 0800 612 9002

Rilmac Asbestos - Nottingham
Stapleford Road Trowell Nottingham NG9 3RP United Kingdom

Rilmac Asbestos - Huddersfield
Heritage Exchange, Wellington Mills, Plover Road, Lindley, Huddersfield, HD3 3HR

Tel: 0800 612 9002

Rilmac Holdings LTD
Crofton Drive, Allenby Road Industrial Estate, Lincoln, Lincolnshire LN3 4NJ

Tel: 01522 531711
Fax: 01522 510291

What Our Clients Say

"Great job on the clamp system! Fitted perfectly, we were more than happy with them."

Rob Legate
FreeWatt